McGowan Demolition Project

McGowan Demolition Project

Published: 3 August 2026

McGowan Lodge at Sundale’s Nambour property was built in 1970, thanks to a generous bequest from Mrs McGowan. Her legacy provided a home for hundreds of Sunshine Coast residents over five decades. However, the building was closed in 2022 as it no longer met the safety and quality standards expected by the community and regulators. After being closed for four years, we are finally progressing with demolition. This is a big step forward for the safety and amenity of our Nambour site and the community.

McGowan Demolition Project

McGowan Lodge at Sundale’s Nambour property was built in 1970, thanks to a generous bequest from Mrs McGowan. Her legacy provided a home for hundreds of Sunshine Coast residents over five decades.

However, the building was closed in 2022 as it no longer met the safety and quality standards expected by the community and regulators.

After being closed for four years, we are finally progressing with demolition. This is a big step forward for the safety and amenity of our Nambour site and the community.

 

Key dates

  • Note – the below dates may change. We will update timelines if required as the project progresses.
  • 17 August: Site established, with fencing and site offices.
  • 17 August: Stage one of asbestos removal and demolition commences (far building on Doolan Street).
  • 26 August: Stage 2 commences (middle building)
  • 23 September: Stage 3 commences (near Sunvilla / care centres)
  • 2-6 November: Groundworks, including grading and grass seeding
  • 10 November: Expected completion / handover.

 

What’s happening during construction

Access and Parking

  • The Doolan Street entrance will be closed throughout the works; access will be via Carter Road only.
  • A temporary footpath will be built along Doolan street to ensure there is safe access to the bus stops.
  • Parking will still be available on site, but there will be fewer car parks to ensure safe space for construction.

Dust and noise

  • We have worked with the demolition contractor to develop very detailed plans to minimise dust, noise, and traffic disruption during the works.
  • Noise and dust will be continuously monitored throughout, and techniques like hosing down the site with water will be used to control the dust.

Safety & Security

  • We are stepping up security during the project, with additional security personnel on overnight, and CCTV cameras installed at the project site.

Asbestos removal

Like many buildings built in the 1970s, McGowan Lodge contains asbestos.

Asbestos removal is highly regulated in Australia. A specialist asbestos hygienist has been engaged to ensure the safe and compliant removal of this material. Once the removal is complete, and signed off, demolition of McGowan will begin.

Landscaping

To improve visibility and safety around our buildings, the trees and shrubs around McGowan will be removed or their canopies will be lifted.

Here are some of the ways the contractors
are managing the safe removal of asbestos.

Removing small amounts at a time and placing into sealed plastic bags immediately

Continuous monitoring on site every day

Using techniques like hosing down areas and spraying fibres so there is no dust

Using protective sheeting to cover areas where removal is taking place

Restricted access and filtration systems

FAQs

More Stories

Celebrating Our Dedicated Volunteers at the 2026 Volunteer Service Awards

Every volunteer brings something special to the Sundale community. Whether it's offering...

Celebrating a Lifetime of Service: Honoring Muriel Peters and Betty Jenkins

At Sundale, community is built through connection, compassion and the people...

Top 10 Questions to Ask Before Choosing a Retirement Community
Top 10 Questions to Ask Before Choosing a Retirement Community

Choosing where to spend your next chapter is one of...