A new chapter for the McGowan grounds

A new chapter for the McGowan grounds

Published: 18 November 2026

McGowan Lodge at Sundale’s Nambour property was built in 1970, thanks to a generous bequest from Mrs McGowan. Her legacy provided a home for hundreds of Sunshine Coast residents over five decades. However, the building was closed in 2022 as it no longer met the safety and quality standards expected by the community and regulators. After being closed for four years, we are finally progressing with demolition. This is a big step forward for the safety and amenity of our Nambour site and the community.

A new chapter for the McGowan grounds

Updated: Wednesday, 18 November 2026

Demolition of McGowan Lodge at Sundale’s Nambour community is complete, with works finished on schedule. Attention now turns to bringing greenery back to the grounds.

Following a site walk-through with the demolition contractors and asbestos removal specialists, the next steps are to lay turf, spread grass seed and install irrigation. Further landscaping will include re-establishing the rose garden as a place for remembrance and reflection.

Fencing will remain in place to give the new grass time to grow, with minor adjustments planned for our community Christmas event. Power has also been reconnected to lighting around the demolition area.

Thank you to our residents, customers, families, neighbours and visitors for your patience throughout the works, and to Team Sundale and our contractors for bringing this stage of the project to completion. We look forward to welcoming our community for the Christmas celebrations.

 

Demolition works: background and original schedule

Project information

McGowan Lodge at Sundale’s Nambour property was built in 1970, thanks to a generous bequest from Mrs McGowan. Her legacy provided a home for hundreds of Sunshine Coast residents over five decades.

However, the building was closed in 2022 as it no longer met the safety and quality standards expected by the community and regulators.

After being closed for four years, we are finally progressing with demolition. This is a big step forward for the safety and amenity of our Nambour site and the community.

Key dates

  • Note – the below dates may change. We will update timelines if required as the project progresses.
  • 17 August: Site established, with fencing and site offices.
  • 17 August: Stage one of asbestos removal and demolition commences (far building on Doolan Street).
  • 26 August: Stage 2 commences (middle building)
  • 23 September: Stage 3 commences (near Sunvilla / care centres)
  • 2-6 November: Groundworks, including grading and grass seeding
  • 10 November: Expected completion / handover.

 

What’s happening during construction

Access and Parking

  • The Doolan Street entrance will be closed throughout the works; access will be via Carter Road only.
  • A temporary footpath will be built along Doolan street to ensure there is safe access to the bus stops.
  • Parking will still be available on site, but there will be fewer car parks to ensure safe space for construction.

Dust and noise

  • We have worked with the demolition contractor to develop very detailed plans to minimise dust, noise, and traffic disruption during the works.
  • Noise and dust will be continuously monitored throughout, and techniques like hosing down the site with water will be used to control the dust.

Safety & Security

  • We are stepping up security during the project, with additional security personnel on overnight, and CCTV cameras installed at the project site.

Asbestos removal

Like many buildings built in the 1970s, McGowan Lodge contains asbestos.

Asbestos removal is highly regulated in Australia. A specialist asbestos hygienist has been engaged to ensure the safe and compliant removal of this material. Once the removal is complete, and signed off, demolition of McGowan will begin.

Landscaping

To improve visibility and safety around our buildings, the trees and shrubs around McGowan will be removed or their canopies will be lifted.

Here are some of the ways the contractors
are managing the safe removal of asbestos.

Removing small amounts at a time and placing into sealed plastic bags immediately

Continuous monitoring on site every day

Using techniques like hosing down areas and spraying fibres so there is no dust

Using protective sheeting to cover areas where removal is taking place

Restricted access and filtration systems

FAQs

Questions or feedback

Keeping our residents, families and neighbours informed throughout the McGowan Demolition Project is important to us. If you have a question, would like to provide feedback, or have a concern about the demolition works, we’d like to hear from you.

Please click here to submit your feedback via our online feedback form.

When completing the form, please select “Construction Project – McGowan (Demolition Site)” under the Site/Service field. This will ensure your enquiry is directed to the appropriate project team for review and response.

 

More Stories

Meet the winners of the Sundale Sunny Awards 2026

In September, we held our first Sundale Sunny Awards, a...

Walking alongside John from Sundale Coolum Waters

A chance conversation at Sundale Coolum Waters Care Centre led...

Sundale Enrolled Nurse Kim, who began her career as a Domestic Assistant
From Domestic Assistant to Enrolled Nurse: Kim’s career at Sundale

When Kim joined Sundale’s In-Home Care team 12 years ago...